Authors
- Disclosure Date
- 2024/08/14
- Disclosure Status
- Disclosed
- Doc Name
- Tonga - EAST ASIA AND PACIFIC- P154840- Pacific Resilience Program - Procurement Plan
- Lending Instrument
- Investment Project Financing
- Pages
- 11
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- TO-Pacific Resilience Program-1370537 -- P154840
- TF No/Name
- TF0A1232-Pacific Resilience Program - Tonga - GFDRR Cofininancing Grant (RE),TF0A2272-Pacific Resilience Program - Tonga - GFDRR Supervision Grant (BE),TF0A6996-BETF: Post-Cyclone Gita JIT Support for Activation of Contingent Emerge,TF0A7818-Additional Financing of the Pacific Resilience Project Tonga under Paci,TF0A8809-Tonga PREP Supervision APIP BETF,TF0B2001-Strengthening housing resilience and multi-hazard early warning capacit,TF0B3990-STRENGTHENING HYDRO-METEOROLOGICAL AND EARLY WARNING SYSTEMS IN THE PAC,TF0B7859-Support to Rapid Post-Disaster Assessment and Recovery Planning in Tong,TF0B7860-Support to Rapid Post-Disaster Assessment and Recovery Planning in Tong,TF0B7883-Disaster Risk Quantification, Financing, and Policy reforms for Resilie,TF0C2126-Supervision Grant for Pacific Resilience Program, Tonga - PPIUF
- Unit Owning
- INF-EAP-Urban 1 (IEAU1)
- Version Type
- Final
Table of Contents
- Nov 6 2017 1
- I. General 1
- 1. Banks approval Date of the procurement Plan 1
- November 23 2015 Revision June 10 2017 1
- 2. Nov 17 2015 1
- Date of General Procurement Notice 1
- 3. June 2017-Dec 2018 1
- Period covered by this procurement plan 1
- II. Goods and Works and non-consulting services. 1
- 1. Prior Review Threshold 1
- Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement 1
- 2. Prequalification 1
- . Bidders for shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 1
- Not applicable 1
- Nov 6 2017 2
- 3. Proposed Procedures for CDD Components as per paragraph. 3.17 of the Guidelines 2
- Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable 2
- 4. Reference to if any Project OperationalProcurement Manual 2
- Project Operational Manual that includes a Procurement Section was approved on November 19 2015 2
- 5. Any Other Special Procurement Arrangements 2
- 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness including those that are subject to retroactive financing and advanced procurement 2
- List the Packages which require Banks prior review first and then the other packages 2
- III. Selection of Consultants 2
- 1. Prior Review Threshold 2
- Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants 2
- Nov 6 2017 3
- 2. Short list comprising entirely of national consultants 3
- 300000 3
- 3. Any Other Special Selection Arrangements 3
- 4. Consultancy Assignments with Selection Methods and Time Schedule works goods services 3
- Nov 6 2017 4
- Nov 6 2017 5