- Environmental and Social Management Framework (ESMF) Türkiye Earthquake Recovery and Reconstruction Project (P180849)
- Lending Instrument
- Investment Project Financing
- Pages
- 114
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- TR-Türkiye Earthquake Recovery And Reconstruction Project -- P180849
- TF No/Name
- TF0C1273-Support to Türkiyeâs Resilient and Inclusive Post-Earthquake Re
- Unit Owning
- Infra ECA Urban (IECUR)
- Version Type
- Final
Files
Table of Contents
- TÜRKİYE EARTHQUAKE RECOVERY AND RECONSTRUCTION PROJECT TERREP 1
- P180849 1
- ENVIRONMENTAL AND SOCIAL MANAGEMENT 1
- FRAMEWORK ESMF 1
- Table of Contents 4
- 1. INTRODUCTION ..................................................................................................... 7 4
- 2. PROJECT DESCRIPTION ........................................................................................... 8 4
- 3. ENVIRONMENTAL AND SOCIAL POLICIES REGULATIONS AND LAW ....................... 13 4
- 3.1. Legal Framework of Türkiye .................................................................................. 13 4
- 3.2. National Environmental and Social Assessment and Permitting .......................... 15 4
- 3.3. World Bank Standards and Key Gaps with the National Framework ................... 17 4
- 4. ENVIRONMENTAL AND SOCIAL BASELINE .............................................................. 22 4
- 4.1. Seismicity .............................................................................................................. 22 4
- 4.2. Biodiversity ............................................................................................................ 24 4
- 4.3. Water Resources and Consumption ..................................................................... 27 4
- 4.4. Waste ................................................................................................................... 28 4
- 4.5. Wastewater Management ................................................................................... 30 4
- 5. POTENTIAL ENVIRONMENTAL AND SOCIAL RISKS AND STANDARD MITIGATION 4
- MEASURES .................................................................................................................. 34 4
- 5.1. Positive Environmental and Social Impacts .......................................................... 34 4
- 5.2. Adverse Environmental and Social Risks and Impacts .......................................... 34 4
- 6. PROCEDURES AND IMPLEMENTATION ARRANGEMENTS ....................................... 37 4
- 6.1. Environmental and Social Risk Management Procedures .................................... 37 4
- 6.2. Implementation Arrangements ............................................................................ 41 4
- 6.3. Proposed Training and Capacity Building ............................................................. 43 4
- 6.4. Estimated Budget .................................................................................................. 45 4
- 7. STAKEHOLDER ENGAGEMENT DISCLOSURE AND CONSULTATIONS .......................... 46 4
- 7.1. Stakeholder Engagement Plan .............................................................................. 46 4
- 7.2. Stakeholder Consultation ......................................... 4
- Error Bookmark not defined. 4
- 7.3. Mechanism ......................................................................................... 46 4
- 7.4. Disclosure and Consultation ................................................................................. 49 4
- List of Tables 4
- List of Figures Annexes 5
- 1. Introduction 8
- 2. Project Description 9
- 3. Environmental and Social Policies Regulations and Law 14
- 4. Environmental and Social Baseline 23
- 5. Potential Environmental and Social Risks and Standard Mitigation Measures 35
- 6. Procedures and Implementation Arrangements 38
- 7. Stakeholder Engagement Disclosure and Consultations 47
- Annex-1. National Environmental including OHS Legislation and International Agreements and Conventions Applicable to the Project Activities 51
- Annex-2. Türkiyes State-led Post-Disaster Rural Housing Reconstruction Program 57
- Annex-3. SCREENING FORM 58
- Annex-4. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN ESMP 64
- Annex-5. SIMPLIFIED SITE-SPECIFIC ESIA INCLUDING ESMP TEMPLATE FOR SUBSTANTIAL RISK PROJECTS 81
- Annex-6. MINUTES OF MEETING 83
- FOR PUBLIC CONSULTATION ON THE ESMF 83
- Annex-7. RISK CATEGORIES OF THE WORLD BANK 84
- Annex-8. WASTE MANAGEMENT PLAN 86
- 1. Purpose and Scope 86
- 2. Legislative Requirements and Standards 87
- 3. Requirements of World Bank ESF 89
- 4. Roles and Responsibilities 91
- 5. Waste Management 92
- 6. Monitoring and Reporting 95
- 7. Training 96
- 8. Review and Update 96
- ANNEX-1 Waste Log Form 97
- ANNEX-2. Waste Management Inspection Checklist 98
- Annex-9. CHANCE FIND PROCEDURE 99
- 1. INTRODUCTION 99
- 2. ROLES AND RESPONSIBILITIES 100
- 3. CHANCE FIND PROCESS 100
- MONITORING AND REPORTING 103
- Annex A. Reporting of Chance Finds Notification Form 104
- ANNEX- B. CHANCE FIND RECORD 107
- ANNEX- C. CONTACT INFORMATION 108
- Annex-10 OCCUPATIONAL HEALTH AND SAFETY PLAN OUTLINE 109
- Annex-11 COMMUNITY SAFETY AND TRAFFIC MANAGEMENT PLAN OUTLINE 111
- Annex-12 POLLUTION PREVENTION PLAN OUTLINE 113