The review was informed by the following principles and considerations: • Facilitate the integration of these plants into the NEM – the technical requirements should support the operation of the power system for secure and reliable operation and not hinder greater participation of these plant in the market. [...] Since DER are expected to play a significant role in the power system of the future – and increasingly, in the power system of the present day – the ability of sub-5 MW DER to support the operation of the power system is also important, especially under emergency conditions where market arrangements alone may not be sufficient and system operations require additional measures to target resilience. [...] © AEMO 2024 | Technical Requirements for 200 kW – 5 MW Distributed Energy Resources 23 Prospective performance requirements • Where the plant is part of a hybrid system, being any combination of load and generation and storage, where the plant is controlling the net import or export at the connection point, and the ramp rate limit is applied to the net import or export, but the plant may be permit. [...] Some control modes may also cause the plant to respond to voltage disturbances in a way that opposes the disturbance (such as volt-var control), in which case the response of the plant also influences the 32 However, some requirements of AS4777.2 2020 exceed the requirements of the NER S5.2. [...] • Where the DNSP and the DER operator can agree another location for the reference point of applicability between the connection point and the DER terminals, instead of at the DER terminals.
Authors
- Pages
- 80
- Published in
- Australia
Table of Contents
- Technical Requirements for 200 kW to 5 MW DER connections 1
- Contents 6
- 1 Introduction 10
- 1.1 Regulation of sub-5 MW DER 11
- 200 11
- 400 11
- 600 11
- 800 11
- 1000 11
- 1400 11
- 2017 2018 2019 2020 2021 2022 2023 11
- Installed capacirty MW 11
- 100kW to 1 MW 1 MW to 5 MW 11
- 1.2 Review objectives 12
- 1.3 Scope 13
- 1.4 Principles and considerations 17
- 1.5 Approach taken in this review 18
- 1.6 Report structure 19
- 2 Prospective performance requirements 20
- 2.1 Ride-through requirements 20
- 2.2 Controls to support system security and emergency operations 22
- 2.3 Market responses 23
- 2.4 Requirements that support the bulk power system 25
- 2.5 Other prospective technical requirements 25
- 3 Existing performance requirements 27
- 3.1 Current approach for DER technical requirements 27
- 3.2 OEM and developer feedback 30
- 4 Proposed performance requirements 31
- 4.1 Options for specifying the technical requirements 31
- 4.2 Proposed performance levels and alignment with international 37
- 4.3 Proposed settings 46
- 4.4 Application of IEC TS 62786-1 to other technical requirements 46
- 4.5 Application of proposed ASNZS 4777.2-2020 to LV IBR larger than 47
- 200 kVA 47
- 4.6 Comparison of current DNSP requirements and proposed settings 49
- 5 Options for implementation 53
- 5.1 Proposed approach 53
- 5.2 NER implications of the proposed changes to ASNZ 4777.1 54
- 5.3 Compliance management 55
- 5.4 Next steps 56
- 6 Summary of issues for consultation 58
- A1. Proposed settings 59
- A2. Gap analysis ASNZS 4777.2 and recommended settings for 70
- A3. DNSP access requirements 74