Authors
- Disclosure Date
- 2024/11/13
- Disclosure Status
- Disclosed
- Doc Name
- Gambia, The - WESTERN AND CENTRAL AFRICA- P163568- Gambia Electricity Restoration and Modernization Project - Procurement Plan
- Lending Instrument
- Investment Project Financing
- Originating Unit
- Infra AFR Energy 2 (IAWE2)
- Pages
- 9
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- GM-Gambia Electricity Restoration And Modernization Project -- P163568
- TF No/Name
- TF0B3700-Energy Efficiency Strategy for The Gambia (ESMAP / PPIAF),TF0B4023-Gambia, The : Energy Efficiency Strategy for The Gambia,TF0B4098-Building resilience in Gambia water utility
- Unit Owning
- Infra AFR Energy 2 (IAWE2)
- Version Type
- Final
Table of Contents
- Project information The Gambia Electricity Restoration and Modernization Project P163568 1
- Project Implementation agency National Water and Electricity Company NAWEC 1
- Date of the Procurement Plan February 2017 1
- Period covered by this Procurement Plan February 2018 to December 2018 1
- Preamble 1
- The Banks Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 1
- Leased Assets of the Procurement Regulations Leasing may be used for those contracts identified in the Procurement Plan tables. 2
- Procurement of Second Hand Goods of the Procurement Regulations is allowed for those contracts identified in the Procurement Plan tables. 2
- Domestic preference of the Procurement Regulations Goods and Works . 2
- Goods is not applicable 2
- Works is not applicable 2
- Other Relevant Procurement Information. 2