Authors
- Disclosure Date
- 2024/11/11
- Disclosure Status
- Disclosed
- Doc Name
- Sierra Leone - WESTERN AND CENTRAL AFRICA- P172492- Accountable Governance for Basic Service Delivery - Procurement Plan
- Lending Instrument
- Investment Project Financing
- Originating Unit
- EFI-AFR2-GOV-FM & PS-2 (EAWG2)
- Pages
- 6
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- SL-Accountable Governance For Basic Service Delivery -- P172492
- TF No/Name
- TF0C4865-Sierra Leone Climate Finance Strategy
- Unit Owning
- EFI-AFR2-GOV-FM & PS-2 (EAWG2)
- Version Type
- Final
Table of Contents
- Project information Sierra Leone Accountable Governance for Basic Service Delivery P172492 1
- Project Implementation agency Ministry of Finance 1
- Date of the Procurement Plan August 13 2022 1
- Period covered by this Procurement Plan 12 months. 1
- Preamble 1
- The Banks Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 1
- Leased Assets as specified under paragraph 5.10 of the Procurement Regulations Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable 2
- Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is allowed for those contracts identified in the Procurement Plan tables Not Applicable 2
- Domestic preference as specified under paragraph 5.51 of the Procurement Regulations Goods and Works . 2
- Goods is not applicable 2
- Works is not applicable 2
- Other Relevant Procurement Information. None 2