Material Measures and Actions Timeframe Authority / Entity MONITORING AND REPORTING: A REGULAR REPORTING The Recipient shall prepare and submit to the Association Each quarter starting from the Project Effective Date, at the latest, regular monitoring reports on the environmental, social, at the beginning of the month following the past quarter, Project health and safety (ESHS) performance of the [...] For security incidents, the Recipient shall follow a similar approach, reporting information on the date of the incident, the date of the report to the PIU, the nature of the event (e.g., attack on Project sites), the profile and possible motivations of the perpetrators, the type of harm or damage incurred to Project beneficiaries, assets, contractors or personnel, and recipient response. [...] Material Measures and Actions Timeframe Authority / Entity b. In the event of a crisis leading to the activation of the Project’s CERC component, the Recipient shall prepare, consult, adopt, and disclose any E&S instruments which may be required for activities under the CERC component in accordance with the CERC Operations Manual and the CERC ESMF Addendum and the ESSs, and thereafter implement th [...] ANPER, ANERSOL) 2.3 The Recipient undertakes to implement and incorporate Suppliers and in the tender documents, the Terms of Reference and contractors contracts of the Project's suppliers/providers, the clauses relating to OHS specified in the project's ESMF, LMP and any other OHS measures recommended by the sub- project's ESMP. [...] Material Measures and Actions Timeframe Authority / Entity MANAGEMENT OF COMMUNITY HEALTH AND SAFETY RISKS AND SECURITY RISKS The Recipient shall assess Project risks and impacts on the health and safety of the affected communities and adopt measures to address these risks and impacts to be reflected in the Project’s ESMF and subsequent site- Same timeline as for the preparation and implementation
involuntary resettlement gender-based violence personal protective equipment safety at work conditions of employment principle of proportionality security management code of conduct pollution prevention occupational health and safety resource efficiency environmental and social impact assessment transmission line duty of care use of force prior review social and environmental mitigation measure grievance mechanism community health and safety unforeseen circumstance social commitment capacities in support project risk land acquisition and resettlement civil works grievance redress mechanism labor management security personnel use of security environmental and social management plan resettlement action plan resettlement policy framework environmental and social assessments applicable national law project affected persons cultural heritage site security risk quality and relevance rules of conduct distribution and transmission biodiversity management plans electrification master plan

Authors

Borrowing Agency

Disclosure Date
2021/11/11
Disclosure Status
Disclosed
Doc Name
Environmental and Social Commitment Plan (ESCP) - Niger Accelerating Electricity Access Project (Hask?) - P174034
Originating Unit
OPS2DATASHEET
Published in
United States of America
Rel Proj ID
NE-Niger Accelerating Electricity Access Project (Haské) -- P174034,P174034
Unit Owning
Infra AFR Energy 2
Volume No
1

Files

Related Topics

All