cover image: Project Information Document - Electricity Distribution Efficiency Improvement Project - P170230 (English)

20.500.12592/7qhndx

Project Information Document - Electricity Distribution Efficiency Improvement Project - P170230 (English)

8 Nov 2021

The review did authorize the team to appraise and negotiate B. Introduction and Context Country Context 1. The Government of Pakistan (GoP) has made good progress in completing its second year of foundational reforms, with support from the World Bank Group (WBG), to restore financial viability of the power sector and lock in the transition to a low carbon footprint (Program for Affordable and Clea [...] In 1997, the GoP unbundled the Power Wing of the Water and Power Development Authority (WAPDA) into four thermal generation companies (GENCOs), one National Transmission & Despatch Company (NTDC), and ten DISCOs, for subsequent privatization of the unbundled GENCOs and DISCOs. [...] Also, an important part of the RE Policy and the new National Electricity Policy approved in June 2021 is the introduction of competitive bidding for all new generation projects, which will disrupt the three-decades old practice of direct contracting and cost-plus tariffs that led to high power costs. [...] The target date for the commencement of the commercial operation of the wholesale market is April 2022. [...] It will also build the capacity of the sector institutions to implement power sector reforms and support enhancing private participation in the management of the DISCOs.
internet of things social impact occupational health and safety best practice wholesale electricity market current account deficit cost of electricity impact of climate change energy mix investment project financing environmental and social management community health and safety operation and management operational efficiency environmental and social risk classification lack of transparency liquidity need human capital accumulation operations and maintenance efficiency improvement electricity distribution system transmission and distribution network supply of electricity distribution company limited access to finance power sector reform financial viability electricity distribution company collection of bill cost of import fiscal consolidation effort cost generation long-term financial viability contribution of women thermal power plant power generation technology power generation cost federal safety net competitive electricity market electric power company burden of reform

Authors

Saqib,Mohammad

Disclosure Date
2021/11/08
Disclosure Status
Disclosed
Doc Name
Project Information Document - Electricity Distribution Efficiency Improvement Project - P170230
Originating Unit
Infra SAR Energy 1 (ISAE1)
Published in
United States of America
Rel Proj ID
PK-Electricity Distribution Efficiency Improvement Project -- P170230
Total Volume(s)
1
Unit Owning
Infra SAR Energy 1
Volume No
1

Files