Disclosable Version of the ISR - Ibadan Urban Flood Management Project - P130840 - Sequence No : 15 (English)

11 Jan 2022

Though the project has made some progress in some areas the following challenges are being experienced: 1. The implementation of First Pool of Long-Term Investment (Lot 1 and 2) has experienced significant delays and additional 4 contractors have been contracted to speed up the works timetable; 1/11/2022 Page 1 of 6 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Author [...] Therefore, deducing from above, based on the progress that has been achieved so far and the next steps in place to enhance implementation, the project remains at Moderately Unsatisfactory at least until the next implementation mission scheduled in January 2022, wherein an assessment will be made whether to upgrade to Moderately Satisfactory. [...] It Comments: is estimated that the total land area protected will increase significantly once the 1st and 2nd pool of long term investment are implemented. [...] IN01083891 ►Improved institutional coordination on flood risk management in Ibadan (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Not Satisfactory (No) Not Satisfactory (No) Not Satisfactory (No) Satisfactory (Yes) Date 23-May-2014 31-Mar-2021 31-Mar-2021 30-Jun-2022 Much as the Flood risk management and drainage master plan has been development but it has not been ope [...] Intermediate Results Indicators by Components Component 1: Flood Risk Identification, Prevention and Preparedness IN01083893 ►Adoption of flood control assets management plan for Ibadan (Text, Custom) 1/11/2022 Page 3 of 6 The World Bank Implementation Status & Results Report Ibadan Urban Flood Management Project (P130840) Baseline Actual (Previous) Actual (Current) End Target Value None None None
nigeria africa west

Authors

Nkoka,Francis Samson

Disclosure Status
Disclosed
Doc Name
Disclosable Version of the ISR - Ibadan Urban Flood Management Project - P130840 - Sequence No : 15
Originating Unit
Urban Dev. & Services Prac 2 (AFTU2)
Published in
United States of America
Rel Proj ID
NG-Ibadan Urban Flood Management Project -- P130840
Unit Owning
Urban DRM AFR 2 (SAWU1)
Version Type
Buff cover

Files

Related Topics

All