This report provides supporting information for the dataset and an overview of the scope, methodology, assumptions, and definition of terms used in the dataset and its development. [...] A representative cost has been selected for the hypothetical project from the data available, and cost certainty qualified based on the spread and quality of data available. [...] The accuracy / certainty of the cost estimates is targeted at +/- 30% based on the spread and quality of data available and our experience with the impact of the above factors. [...] However, the accuracy band is used to arrive at the cost of a project for certain size, scope of the project, year of completion, level of definition, and its battery limits. [...] The main turbine-specific factor influencing capacity factor is the size of the rotor relative to the rated power output of the generator (i.e., the Specific Power).
Authors
- Pages
- 183
- Published in
- Australia