Authors
- Disclosure Date
- 2024/07/17
- Disclosure Status
- Disclosed
- Doc Name
- Mongolia - EAST ASIA AND PACIFIC- P173799- MONGOLIA COVID-19 EMERGENCY RESPONSE AND HEALTH SYSTEM PREPAREDNESS PROJECT - Procurement Plan
- Lending Instrument
- Investment Project Financing
- Pages
- 12
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- MN-Mongolia Covid-19 Emergency Response And Health System Prepared -- P173799
- Unit Owning
- Health Nutrition&Population EAP2 (HEAH2)
- Version Type
- Final
Table of Contents
- Project information Mongolia COVID-19 emergency response and health system preparedness project P-173779 1
- Project Implementation agency Ministry of Health 1
- Date of the Procurement Plan 25 March 2020 1
- Period covered by this Procurement Plan Apr-Jun 2020 1
- Preamble 1
- The Banks Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 1
- Leased Assets of the Procurement Regulations Leasing may be used for those contracts identified in the Procurement Plan tables. 2
- Procurement of Second Hand Goods of the Procurement Regulations is allowed for those contracts identified in the Procurement Plan tables 2
- Domestic preference of the Procurement Regulations Goods and Works . 2
- Goods Not applicable most if the Goods are not manufactured in country 2
- Works Not applicable no works planned under this Project 2
- Hands-on Expanded Implementation Support HEIS of the Procurement Regulations is Applicable. Under HIES the Project will receive the bank-facilitated procurement BFP. 2
- 2. Assist the Implementing Entity in i negotiating prices delivery terms and other contract conditions with identified suppliers 2
- 3. Draft final award letters andor contracts adapted to specific market conditions on a fit-for-purpose basis and ensuring consistency with Banks procurement framework 2
- 4. Provide additional hands-on support in contracting to outsource logistics. 2
- 5. Draft technical requirements and specifications as requested by the Implementing Entity 2
- 6. Assist the Implementing Entity in drafting procurement documents and 2
- 7. Provide advice on evaluation procedures participate as observers during negotiations by only clarifying matters of the Bank Procurement Regulations. 2
- Other Relevant Procurement Information. 3
- Given the nature of the Project the procurement approach shall prioritize fast track emergency procurement for the required goods works and services that include the following measures 3
- - Direct Contracting andor Limited Competition with identified manufacturers of equipment 3
- - Use of CQS RFQ or National OpenLimited Competitive procurement procedures as appropriate and agreed with the Bank in the Procurement Plan. 3
- - Increasing advance payments to 40 when supported by an advance payment guarantee 3
- - Waiving the conditions for bid securities and replacing them with Bid Securing Declarations 3
- - Maximizing the use of direct payments to foreign suppliers 3
- - Allowing submission of bids using emails in encrypted files where it is not feasible to receive bids in hardcopy. 3
- All procurements under this project will be subject to Post Review there will be no Prior Review. 3
- Thresholds for fast track emergency procurement under the Project are 3
- - Increased threshold for goods for shopping of US500000 3
- - Increased threshold for National Procurement of U1000000 and reduced bidding time to 7-14 days 3
- - Use of CQS rather than QCBS for larger contract below should read above US500000. 3