Authors
- Disclosure Date
- 2024/08/27
- Disclosure Status
- Disclosed
- Doc Name
- Appraisal Project Information Document (PID)
- Lending Instrument
- Investment Project Financing
- Pages
- 11
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- LB-Lebanon Renewable Energy And System Reinforcement Project -- P180501
- TF No/Name
- TF0C2244-Modernizing the Lebanese Electricity Utility Towards Energy Transition
- Unit Owning
- Infra MNA Energy 1 (IMNE1)
- Version Type
- Final
Files
Table of Contents
- The World Bank 1
- The World Bank 2
- BASIC INFORMATION 2
- A. Basic Project Data 2
- Components 2
- PROJECT FINANCING DATA US Millions 2
- Maximizing Finance for Development 2
- Is this an MFD-Enabling Project MFD-EP 2
- Is this project Private Capital Enabling PCE 2
- SUMMARY 2
- Total Operation Cost 250.00 2
- Total Financing 250.00 2
- Financing Gap 0.00 2
- The World Bank 3
- DETAILS 3
- World Bank Group Financing 3
- B. Introduction and Context 3
- In the context of Lebanons ongoing economic financial and energy sector crises the proposed project supports 3
- Lebanons economy has been facing multiple crises for years beginning with an economic and financial meltdown 3
- The World Bank 4
- Five years into the crisis little progress has been made towards a comprehensive resolution plan. 4
- The collapse of the currency coupled with the systemic failure of the banking system has resulted in a pervasive 4
- Severe shortage of electricity services from the grid is a major barrier to economic recovery. 4
- The installed grid-connected electricity generation capacity in Lebanon is about 2300 Megawatt MW primarily 4
- The World Bank 5
- EDL the vertically integrated national utility is responsible for electricity generation transmission and 5
- The electricity sector has been facing several challenges. 5
- With no fiscal space left the Government has been compelled to start reforming a decades-long status quo 5
- A set of initial reform measures implemented by the Government has established the foundation for improved services and financial viability and is the basis for the proposed Bank financing operation. 5
- C. Proposed Development Objectives 5
- The World Bank 6
- D. Project Description 6
- The Project would be the first of a proposed Series of Projects SOP 6
- Component 1 Strengthening of EDL Operational and Commercial Systems 6
- Sub-component 1.1 Strengthening of EDL Operational Systems 6
- Sub-component 1.2 Strengthening of EDL Commercial Systems 6
- Component 2 Increase of Grid-Connected Renewable Energy Supply and Network Reinforcement 6
- The World Bank 7
- Sub-component 2.1 Development of Grid-connected Solar PV Plant 7
- Sub-component 2.2 Rehabilitation of LRA HPPs and Strengthening of Dam Safety 7
- Joun HPP 7
- Awali HPP 7
- Markabi HPP 7
- Dam safety improvement 7
- Sub-component 2.3 Rehabilitation and Reinforcement of EDL Transmission Network 7
- Rehabilitation of Ashrafia 220 kV substation 7
- Rehabilitation of 220 kV Deir Nbouh Baalbek overhead transmission line OHL 7
- Upgrade of Baalbek substation 7
- Connection of solar PV plant to the grid 7
- The World Bank 8
- Component 3 Technical Assistance 8
- Component 4 Contingent Emergency Response Component CERC. 8
- Triggered 8
- The Environmental Risk Classification is Substantial. 8
- The World Bank 9
- The social risk is substantial as potential risks are temporary predictable reversible medium in magnitude and 9
- The implementing agencies EDL and LRA in close coordination with MoEW and with the support of a competent 9
- ES consultancy firm have prepared the following studies and documents 9
- The following instruments will be prepared before commencement of the relevant activities 9
- The World Bank 10
- E. Implementation 10
- EDL and LRA will be the implementing entities for their corresponding investments supported by their respective OEs and reporting to a Project Steering Committee PSC chaired by MOEW. 10
- The core of the PMTs will comprise the following positions 10
- CONTACT POINT 10
- World Bank 10
- BorrowerClientRecipient 10
- Lebanese Republic 10
- Implementing Agencies 10
- Litani River Authority LRA 10
- Electricité du Liban EDL 10
- The World Bank 11
- FOR MORE INFORMATION CONTACT 11
- APPROVAL 11
- Approved By 11