Authors
- Disclosure Date
- 2024/09/25
- Disclosure Status
- Disclosed
- Doc Name
- Disclosable Restructuring Paper - Improving the Performance of Non-Criminal Justice Services - P162833
- Lending Instrument
- Investment Project Financing
- Pages
- 14
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- PE-Improving The Performance Of Non-Criminal Justice Services -- P162833
- Unit Owning
- EFI-LCR-GOV-FM & PS-2 (ELCG2)
- Version Type
- Final
Table of Contents
- Report No RES00405 1
- RESTRUCTURING PAPER 1
- ON A 1
- PROPOSED PROJECT RESTRUCTURING 1
- Improving the Performance of Non-Criminal Justice Services 1
- APPROVED ON 05-Jun-2019 1
- Republic of Peru 1
- Governance Latin America And Caribbean 1
- The World Bank 2
- ABBREVIATIONS AND ACRONYMS 2
- Centros de Asistencia Legal Gratuita 2
- Academia de la Magistratura 2
- Expediente Judicial Electrónico 2
- Junta Nacional de Justicia 2
- Ministerio de Economía y Finanzas 2
- Ministerio de Justicia y Derechos Humanos 2
- Poder Judicial 2
- Sistema Integrado de Gestión de Expedientes 2
- Tribunal Constitucional 2
- Unidad Ejecutora 2
- The World Bank 3
- BASIC DATA 3
- Product Information 3
- Organizations 3
- OPERATION STATUS 3
- Project Development Objective DO 3
- Disbursement Summary in USD million 3
- The World Bank 4
- Policy Waivers 4
- The World Bank 5
- I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING 5
- II. DESCRIPTION OF PROPOSED CHANGES 5
- III. PROPOSED CHANGES 5
- IV. DETAILED CHANGES 5
- The World Bank 6
- I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING 6
- This Restructuring Paper RP seeks the Country Directors approval for a Level 2 restructuring. 6
- A. Project Status 6
- The project was approved by the Board of Executive Directors on June 5 2019. The Loan Agreement Loan No. 8975-PE was signed on November 27 2019 and became effective on December 12 2019. 6
- Component 1 and 2 Strengthening the institutionality of the non-criminal justice administration system and improving the production analysis and use of information of the justice administration. 6
- Component 3 Reducing socio-economic cultural and geographic barriers to access to justice for vulnerable populations. 6
- Component 4 Improving efficiency and efficacy of the justice administration system institutions. 6
- The World Bank 7
- As of September 2024 the projects development objective PDO is rated as Moderately Unsatisfactory MU mainly due to delays in achieving key results by the current closing date. 7
- Additionally the project is rated Moderately Satisfactory MS in financial management Moderately 7
- Satisfactory MS in procurement and Satisfactory S in compliance with social and environmental safeguards. 7
- B. Rationale for Restructuring 7
- In a letter dated September 20 2024 the Ministry of Economy and Finance MEF requested a first extension of the closing date for 11 months to August 31st 2025. 7
- The extension will provide the necessary time to overcome challenge encountered during the first years of project implementation and advance core activities 7
- II. DESCRIPTION OF PROPOSED CHANGES 7
- The World Bank 8
- III. PROPOSED CHANGES 8
- Operation Information Proposed Changes Operation Information Proposed Changes 8
- IV. DETAILED CHANGES 8
- COSTS FINANCING 8
- Private Capital Facilitation 8
- Is this an MFD-Enabling Project MFD-EP 8
- Is this project Private Capital Enabling PCE 8
- The World Bank 9
- LOANS 9
- Loan Closing 9
- LoanCreditTrust Fund Status 9
- Original Closing 9
- Revised Closings 9
- Proposed Closing 9
- Proposed Deadline for Withdrawal Applications 9
- DISBURSEMENTS 9
- Operation Dates Projection Details 9
- The World Bank 10
- The World Bank 11
- The World Bank 12
- The World Bank 13
- The World Bank 14