- Doc Name
- Appraisal Environmental and Social Review Summary (ESRS) - Argentina: Support to the Sustainability and Equity of Public Transport Project - P506846
- Lending Instrument
- Investment Project Financing
- Pages
- 9
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- AR-Argentina: Support To The Sustainability And Equity Of Public T -- P506846
- Unit Owning
- Transport-LAC (ILCT1)
- Version Type
- Final
Table of Contents
- The World Bank 1
- The World Bank 2
- I. BASIC INFORMATION 2
- B. Is the operation being prepared in a Situation of Urgent Need of Assistance or Capacity Constraints as per Bank IPF Policy para. 12 2
- C. Summary Description of Proposed Project Activities 2
- The World Bank 3
- D. Environmental and Social Overview D.1 Overview of Environmental and Social Project Settings 3
- The World Bank 4
- D.2 Overview of Borrowers Institutional Capacity for Managing Environmental and Social Risks and Impacts 4
- II. SUMMARY OF ENVIRONMENTAL AND SOCIAL ES RISKS AND IMPACTS 4
- A. Environmental and Social Risk Classification ESRC 4
- The World Bank 5
- A.1 Environmental Risk Rating 5
- A.2 Social Risk Rating 5
- B. Environment and Social Standards ESS that Apply to the Activities Being Considered 5
- B.1 Relevance of Environmental and Social Standards 5
- ESS1 - Assessment and Management of Environmental and Social Risks and Impacts 5
- The World Bank 6
- ESS10 - Stakeholder Engagement and Information Disclosure 6
- ESS2 - Labor and Working Conditions 6
- ESS3 - Resource Efficiency and Pollution Prevention and Management 6
- The World Bank 7
- ESS4 - Community Health and Safety 7
- ESS5 - Land Acquisition Restrictions on Land Use and Involuntary Resettlement 7
- ESS6 - Biodiversity Conservation and Sustainable Management of Living Natural Resources 7
- ESS7 - Indigenous PeoplesSub-Saharan African Historically Underserved Traditional Local Communities 7
- ESS8 - Cultural Heritage 7
- ESS9 - Financial Intermediaries 7
- B.2 Legal Operational Policies that Apply 7
- OP 7.50 Operations on International Waterways 7
- OP 7.60 Operations in Disputed Areas 7
- B.3 Other Salient Features 7
- The World Bank 8
- Use of Borrower Framework 8
- Use of Common Approach 8
- C. Overview of Required Environmental and Social Risk Management Activities 8
- C.1 What Borrower environmental and social analyses instruments plans andor frameworks are planned or required by implementation 8
- III. CONTACT POINT 8
- World Bank 8
- The World Bank 9
- IV. FOR MORE INFORMATION CONTACT 9
- V. APPROVAL 9