Authors
- Disclosure Date
- 2024/10/16
- Disclosure Status
- Disclosed
- Doc Name
- Malawi - EASTERN AND SOUTHERN AFRICA- P164961- Malawi Governance to Enable Service Delivery Project - Procurement Plan
- Lending Instrument
- Investment Project Financing
- Originating Unit
- EFI-AFR1-GOV-FM & PS-1 (EAEG1)
- Pages
- 12
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- MW-Malawi Governance To Enable Service Delivery Project -- P164961
- TF No/Name
- TF0B9413-Platform for Inclusive Citizen Engagement in Local Service Delivery
- Unit Owning
- EFI-AFR1-GOV-FM & PS-1 (EAEG1)
- Version Type
- Final
Table of Contents
- GOVERNANCE TO ENABLE SERVICE DELIVERY IN MALAWI 1
- PROJECT PREPARATION ADVANCE PPA 1
- PROCUREMENT PLAN 1
- I. General 1
- 1. Project Information 1
- 2. Project Implementation Agency 1
- 3. Date of the Procurement Plan 1
- 4. Period Covered by this procurement plan 1
- II. Preamble 1
- This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. 1
- III. Banks Standard Procurement Documents 1
- IV. National Procurement Arrangements 1
- V. Prequalification NA 2
- VI. Leased Assets 2
- Not Applicable. 2
- VII. Procurement of Second Hand Goods 2
- Not Applicable. 2
- VIII. 2
- Domestic preference Goods and Works 2
- Domestic preference is not applicable for National Open Competitive Procurement 3
- IX. Other Relevant Procurement Information 3
- Provide any other relevant procurement information such as procedures for CDD components Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc.--NONE 3
- X. The project being a non- emergency project there would be generally prior reviews of cases unless specifically indicated in the Procurement Plan as a special measure. 3
- Procurement Prior Review Thresholds US millions Substantial. 3
- The overall Project procurement Risk is 3
- Post Review All contracts not subject to prior review shall be subject to post review. 3
- XI. Procurement Prior Review Thresholds Based on Substantial Risk Rating US millions 3
- XII. Thresholds for procurement approaches and methods 3
- Works Goods IT and Non- Consulting Services 4
- Shortlist of National Consultants 4
- PROCUREMENT PACKAGES WITH METHODS AND TIME SCHEDULES 5
- A. GOODS 5
- B. CONSULTANCY SERVICES 5
- SUMMARY 6
- NO CATEGORY OF PROCUREMENT 6
- VALUE US 6
- TOTAL 6
- Appendix 1 7
- Letter of Acceptance of the World Banks Anti-Corruption Guidelines and Sanctions Framework 7
- Insert name of Employer as per bidding document 7