- Disclosable Restructuring Paper - Ethiopia Economic Opportunities Program - P163829
- Lending Instrument
- Program-for-Results
- Pages
- 26
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- ET-Ethiopia Economic Opportunities Program -- P163829
- TF No/Name
- TF0A7422-Ethiopia Economic Opportunities P4R TA,TF0A9714-PforR Financing for Economic Opportunities Program DLIs,TF0A9715-Invesment Project Financing for the Economic Opportunities Program,TF0B0588-Employment Promotion and Protection Pilot IE,TF0B7730-Experimental and Survey Evidence on Economic Inclusion of Refugees in E,TF0C1543-Ethiopia Economic Opportunities Program-Employment, Livelihood and Prot
- Unit Owning
- EFI-AFR1-FCI-Finance-1 (EAEF1)
- Version Type
- Final
Table of Contents
- Report No RES00518 1
- INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT ANDOR 1
- INTERNATIONAL DEVELOPMENT ASSOCIATION 1
- RESTRUCTURING PAPER 1
- ON A 1
- PROPOSED PROGRAM RESTRUCTURING 1
- Ethiopia Economic Opportunities Program 1
- APPROVED ON 26-JUN-2018 1
- Finance Competitiveness and Innovation Eastern And Southern Africa 1
- The World Bank 2
- CURRENCY EQUIVALENTS 2
- Exchange Rate Effective Oct 24 2024 2
- Currency Unit Ethiopian Birr ETB 2
- ETB 121.69 US1 2
- US 1.33 SDR 1 2
- FISCAL YEAR July 8 July 7 2
- The World Bank 3
- ABBREVIATIONS AND ACRONYMS 3
- The World Bank 4
- BASIC DATA 4
- Product Information 4
- ACCOUNTABILITY 4
- RegionCountry 4
- Implementing Unit 4
- The World Bank 5
- OPERATION STATUS 5
- Development Objective DO 5
- Disbursement Summary in USD million 5
- Policy Waivers 5
- The World Bank 6
- I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING 6
- II. DESCRIPTION OF PROPOSED CHANGES 6
- III. PROPOSED CHANGES 6
- IV. DETAILED CHANGES 6
- ANNEX 1 RESULTS 6
- ANNEX 2 PROGRAM ACTION PLAN 6
- The World Bank 7
- I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING 7
- Background 7
- EOP has disbursed 134.76 of its 239.11m in financing commitments. 7
- This is the fourth restructuring of EOP. 7
- The cancellation of FCDO funding has substantially impacted the EOPs budget. 7
- The program has made significant progress in the implementation of the DLRs and the technical assistance. 7
- The World Bank 8
- The rationale for this restructuring is to extend the closing date of TF C1543 to align with the Program closing date of December 31 2024. 8
- II. DESCRIPTION OF PROPOSED CHANGES 8
- III. PROPOSED CHANGES 8
- Operation Information Proposed Changes Operation Information Proposed Changes 8
- The World Bank 9
- IV. DETAILED CHANGES 9
- COSTS FINANCING 9
- Is this an MFD-Enabling Project MFD-EP 9
- Is this project Private Capital Enabling PCE 9
- LOANS 9
- Loan Closing 9
- LoanCreditTrust Fund Status 9
- Original Closing 9
- Revised Closings 9
- Proposed Closing 9
- Proposed Deadline for Withdrawal Applications 9
- LEGAL 9
- Environmental Assessment EA Category 9
- Safeguard Policies Triggered 9
- Triggered 9
- Policies Current 9
- Explanation required if rating changes 9
- The World Bank 10
- The World Bank 11
- The World Bank 12
- The World Bank 13
- The World Bank 14
- The World Bank 15
- The World Bank 16
- The World Bank 17
- The World Bank 18
- The World Bank 19
- The World Bank 20
- The World Bank 21
- Delete this note when finalizing the document. 21
- The World Bank 22
- ANNEX 2 PROGRAM ACTION PLAN 22
- Action Description Source DLI Responsibility Timing 22
- Completion Measurement Action 22
- Delete this note when finalizing the document. 22
- The World Bank 23
- The World Bank 24
- The World Bank 25
- The World Bank 26
- Proposed 26
- Action Description Source DLI Responsibility Timing Completion Measurement 26