Authors
- Disclosure Date
- 2024/11/07
- Disclosure Status
- Disclosed
- Doc Name
- Disclosable Restructuring Paper - Earthquake Recovery and Public Health Preparedness Project - P173998
- Lending Instrument
- Investment Project Financing
- Pages
- 16
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- HR-Earthquake Recovery And Public Health Preparedness Project -- P173998
- TF No/Name
- TF0B2898-Croatia E-Education for Pregnancy and Parenting during COVID-19,TF0B9214-Supporting disaster resilience in Croatia
- Unit Owning
- Infra ECA Urban (IECUR)
- Version Type
- Final
Table of Contents
- Report No RES00313 1
- RESTRUCTURING PAPER 1
- ON A 1
- PROPOSED PROJECT RESTRUCTURING 1
- EARTHQUAKE RECOVERY AND PUBLIC HEALTH PREPAREDNESS PROJECT 1
- APPROVED ON 26 JUNE 2020 1
- REPUBLIC OF CROATIA 1
- Urban Resilience and Land Europe And Central Asia 1
- The World Bank 2
- ABBREVIATIONS AND ACRONYMS 2
- The World Bank 3
- BASIC DATA 3
- Product Information 3
- Organizations 3
- OPERATION STATUS 3
- Project Development Objective DO 3
- Disbursement Summary in USD million 3
- The World Bank 4
- Policy Waivers 4
- The World Bank 5
- I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING 5
- II. DESCRIPTION OF PROPOSED CHANGES 5
- III. PROPOSED CHANGES 5
- IV. DETAILED CHANGES 5
- The World Bank 6
- I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING 6
- A. Introduction 6
- This Second Restructuring Paper is prepared Earthquake Recovery and Public Health Preparedness Project P173998 Project 6
- B. Project Background 6
- The Project implementation 6
- The World Bank 7
- C. Project Status 7
- The Project has disbursed 16 percent of the loan to this date. 7
- Component 1 7
- Rehabilitation and Reconstruction of Health and Education Facilities Support for Public Reconstruction 7
- KBC Zagreb REBRO Phase III 7
- CIPH Nazorova 53 building 7
- KBC Zagreb pediatric hematology and oncology ward 7
- The World Bank 8
- Petrinja Vocational Secondary School 8
- Petrinja teaching faculty dormitory in Sisak County 8
- Faculty of Electrical Engineering FER designs only 8
- Component 2 8
- The World Bank 9
- Component 3 9
- Summary of environmental and social ES risks compliance 9
- D. Rationale For Restructuring 9
- The World Bank 10
- II. DESCRIPTION OF PROPOSED CHANGES 10
- Summary of changes. 10
- Closing date extension and the Results Framework 10
- Disbursement estimates. 10
- III. PROPOSED CHANGES 10
- Operation Information Proposed Changes Operation Information Proposed Changes 10
- The World Bank 11
- IV. DETAILED CHANGES 11
- COSTS FINANCING 11
- Private Capital Facilitation 11
- Is this an MFD-Enabling Project MFD-EP 11
- Is this project Private Capital Enabling PCE 11
- LOANS 11
- Loan Closing 11
- LoanCreditTrust Fund Status 11
- Original Closing 11
- Revised Closings 11
- Proposed Closing 11
- Proposed Deadline for Withdrawal Applications 11
- DISBURSEMENTS 11
- Operation Dates Projection Details 11
- The World Bank 12
- ENVIRONMENTAL SOCIAL 12
- Environmental Social Assessment 12
- The World Bank 13
- The World Bank 14
- The World Bank 15
- The World Bank 16