- Disclosable Restructuring Paper - Ferghana Valley Rural Enterprise Development Project - P166305
- Lending Instrument
- Investment Project Financing
- Pages
- 21
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- UZ-Ferghana Valley Rural Enterprise Development Project -- P166305
- TF No/Name
- TF0A9865-Improving Climate Resilience in Rural Enterprises in Uzbekistan,TF0A9881-ECAPDEV Grant to Ferghana Valley Enterprise Development Project
- Unit Owning
- Agriculture and Food PG ECA (SCAAG)
- Version Type
- Final
Table of Contents
- Report No RES00360 1
- RESTRUCTURING PAPER 1
- ON A 1
- PROPOSED PROJECT RESTRUCTURING 1
- Ferghana Valley Rural Enterprise Development Project 1
- APPROVED ON 21-Mar-2019 1
- Republic of Uzbekistan 1
- Agriculture and Food Europe And Central Asia 1
- The World Bank 2
- ABBREVIATIONS AND ACRONYMS 2
- The World Bank 3
- The World Bank 4
- BASIC DATA 4
- Product Information 4
- Organizations 4
- OPERATION STATUS 4
- Project Development Objective DO 4
- Disbursement Summary in USD million 4
- The World Bank 5
- Policy Waivers 5
- The World Bank 6
- I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING ...................................................................................1 6
- II. DESCRIPTON OF PROPOSED CHANGES 6
- III. PROPOSED CHANGES........................................................................................................................................6 6
- IV. DETAILED CHANGES .......................................................................................................................................6 6
- The World Bank 7
- I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING 7
- Progress towards achievement of PDO 7
- Satisfactory 7
- Implementation Progress 7
- Moderately Satisfactory e 7
- Component 1 Enterprise Development 7
- The World Bank 8
- Component 2 Access to Finance 8
- Component 3 Project Management and Coordination 8
- Rationale for Restructuring 8
- Agriculture machinery leasing services. 8
- The World Bank 9
- Change in the institutional arrangement of the Project. 9
- The World Bank 10
- II. DESCRIPTON OF PROPOSED CHANGES 10
- Introduction of a new subcomponent on agriculture machinery leasing Subcomponent 2.3 and reallocation of 10
- US19.5 million of currently unutilized fund under the Project. 10
- Table 1 Cost Re-allocation IBRD US million 10
- Original Revised 10
- Component 1 Enterprise Development 15.0 10.0 10
- Component 2 Access to Finance 167.0 186.5 10
- Component 3 Project Management and Coordination 10
- 18.0 3.5 10
- The World Bank 11
- Total 200.0 200.0 11
- Change in the implementation arrangement of the Project. 11
- Change in the disbursement categories. 11
- Revisions of Results Framework indicators. 11
- Table 2 Changes in the Results Framework 11
- Environmental and Social ES instruments 11
- The World Bank 12
- III. PROPOSED CHANGES 12
- Operation Information Proposed Changes Operation Information Proposed Changes 12
- IV. DETAILED CHANGES 12
- COMPONENTS 12
- Current 12
- Component Name 12
- Current Cost USD Action Proposed 12
- Component Name 12
- Proposed Cost USD 12
- The World Bank 13
- TOTAL 185000000.00 200000000.00 13
- COSTS FINANCING 13
- Private Capital Facilitation 13
- Is this an MFD-Enabling Project MFD-EP 13
- Is this project Private Capital Enabling PCE 13
- LOANS 13
- Reallocations 13
- IBRD-89380-001 13
- Financing Type Total 13
- Category No. 13
- Expenditure Category 13
- Current Allocation 13
- Actuals Committed 13
- Proposed Allocation Current Proposed 13
- Total 200000000.0 0 13
- 200000000.0 0 13
- LEGAL 13
- The World Bank 14
- Environmental Assessment EA Category 14
- Safeguard Policies 14
- Triggered 14
- Policies Current 14
- Explanation required if rating changes 14
- Legal Covenants 14
- LoanCreditTF Description Status Action 14
- Conditions 14
- The World Bank 15
- The World Bank 16
- The World Bank 17
- The World Bank 18
- The World Bank 19
- The World Bank 20
- The World Bank 21