cover image: HUNTER VALLEY NOVEMBER MAJOR NORTH CLOSEDOWN  - Hunter Valley Closedown Briefing Document

HUNTER VALLEY NOVEMBER MAJOR NORTH CLOSEDOWN - Hunter Valley Closedown Briefing Document

17 Nov 2023

Where practical IBAs are to be emailed to the NCCNIBA@artc.com.au the day prior to the Closedown, the IBA must contain the Network Control Board for the IBA in the Subject field. [...] Full road and pedestrian closure with specific Safe Notice for the removal of Hand Signallers Before booking out level crossing warning equipment the Competent Worker must check with the PPO to ensure no rail traffic is approaching the level crossing and advise the PPO of the name and contact number of the Handsignaller at the level crossing. [...] Once agreement is reached on the worksite protection arrangements, the Coordinating Protection Officer must contact the PPO and advise the agreed arrangements of the Coordinated Worksite. [...] New Worksites Entering the LPA: Where a new workgroup is to establish a worksite in a section where Lookout Working is in place • The PPO must advise the PO of the workgroup of the Lookout Working workgroup contact details and the Lookout Working limits, • The new workgroup PO must contact the PO for the Lookout Working workgroup and make agreed arrangements for the works to be completed, • If the. [...] Entering an existing worksite: Prior to entering an existing worksite in the corridor, the PO for the Lookout Working Workgroup must: • Contact the PO for the worksite and, • Gain authority from the PO to enter the pre-existing worksite and, • Get briefed into the worksite by the PO, and • Inform the PPO that the Lookout Working Workgroup has entered an existing worksite location Exiting an existi.

Authors

George Randle

Pages
11
Published in
Australia