If a Facility or Separately Certified Component fails a Reserve Capacity Test, AEMO will: (a) notify the Market Participant that the Facility or Separately Certified Component has failed the Reserve Capacity Test; (b) provide the Market Participant with a copy of the results of the Test; and (c) where the Reserve Capacity Test was a first Test, re-test the Facility or Separately Certified Componen. [...] If a Facility or Separately Certified Component passes the Reserve Capacity Test, AEMO will: (a) notify the Market Participant that the Facility or Separately Certified Component has passed the Reserve Capacity Test; and (b) provide a copy of the results of the Test. [...] AEMO will deem a Reserve Capacity Test to be an Invalid Test if: (a) the temperature measured by the Temperature Measurement System specified in WEMS for the Facility is outside of the range 0°C to 45°C, and paragraph 5.2.3(b) does not apply; (b) AEMO considers that there is an error in the data used to determine the results of the Test, such an error or errors in Meter Data Submissions, including. [...] Where a Market Participant does not provide Meter Data Submissions from Facility Sub- Metering for either the first or second Reserve Capacity Test by the time determined under clause 4.25.2C, AEMO will notify the Market Participant that the Capacity Credits assigned to the relevant Facility or Separately Certified Component will be reduced to zero and the effective date for the reduction. [...] AEMO will record the following about Reserve Capacity Tests: (a) information regarding the conduct of the Reserve Capacity Test; © AEMO | 1 October 2024 Page 14 of 17 WEM Procedure: Reserve Capacity Testing (b) the results of the Reserve Capacity Test; (c) the determination of the outcome of the Reserve Capacity Test (passed or failed); and (d) information regarding any action taken in accordance.
Authors
- Pages
- 17
- Published in
- Australia
Table of Contents
- Version Release History 2
- Contents 3
- Tables 3
- 1. Introduction 4
- 1.1. Purpose and scope 4
- 1.2. Definitions 4
- 1.3. Interpretation 5
- 1.4. Related documents 5
- 1.5. Communications and provision of information 6
- 2. Preparatory steps 6
- 2.1. Temperature Dependence Curves 6
- 2.2. Temperature measurement sources 8
- 2.3. Required Level calculation 9
- 3. Verification by Observation for Non-Intermittent Generating Systems or Electric Storage Resources 10
- 4. Verification Tests for Demand Side Programmes 11
- 5. Reserve Capacity Tests 11
- 5.1. Conducting Reserve Capacity Tests 11
- 5.2. Assessing the results of Reserve Capacity Tests 12
- 5.3. Capacity Credit reductions 14
- 5.4. Reserve Capacity re-test under clause 4.25.5 14
- 5.5. Recording and publishing Reserve Capacity Test results 14
- 6. Reviewing results 15
- Appendix A. Relevant clauses of the WEM Rules 17