Authors
- Disclosure Date
- 2024/10/13
- Disclosure Status
- Disclosed
- Doc Name
- Viet Nam - EAST ASIA AND PACIFIC- P166656- Vietnam University Development of VNU-Hanoi, VNU-HCM, and UD - Procurement Plan
- Lending Instrument
- Investment Project Financing
- Originating Unit
- Education EAP (HEAED)
- Pages
- 69
- Product Line
- IBRD/IDA
- Published in
- United States of America
- Rel Proj ID
- VN-Vietnam University Development Of Vnu-Hanoi, Vnu-Hcm, And Ud -- P166656
- Unit Owning
- Education EAP (HEAED)
- Version Type
- Final
Table of Contents
- Indicator Unit End targets 10
- Area of the works for improvement of learning and teaching quality to be constructed. 10
- - VNU-HN 58977. - UD 94923. - VNU-HCMC 25605. 10
- Area of the works for research and technology transfer to be constructed. 10
- - VNU-HN 110977. - UD 31500. - VNU-HCMC 50246. 10
- Students satisfaction of learning experience 10
- - VNU-HN increase from 70 from 2019 to 80 by 2025. - UD increase from 70 from 2019 to 80 by 2025. - VNU-HCMCincrease from 63 from 2019 to 10
- 80 by 2025. 11
- The number of articles published in Web of Science and Scopus journals 11
- - VNU-HN increase from 8240 articles in 2019 to 13500 articles in 2025. - UD increase from 240 articles in 2019 to 420 articles in 2025. - VNU-HCMC increased from 3775 in 2019 to 11140 in 2025. 11
- The number of internationally accreditated programs 11
- - VNU-HN increase from 32 programs in 2019 to 52 programs in 2025. - UD increase from 04 programs in 2019 to 23 programs in 2025. - VNU-HCMC increased from 73 programs in 2019 to 102 programs in 2025. 11
- The number of domestic and international partners 11
- - VNU-HN increase from 23 in 2019 to 50 in 2025. - UD from 10 in 2019 to 95 in 2025. - VNU-HCMC increase from 20 in 2019 to 50 in 2025. 11
- The graduation rate on time for programs applying innovative technologies 11
- - VNU-HN from 64 in 2019 to 80 in 2025. - UD from 70 in 2019 to 80 in 2025. - VNU-HCMC from 55 in 2019 to 75 in 2025. 11
- A list of prospective contractors is provided in the Appendix 26
- A list of prospective suppliers in Viet Nam is provided in the Appendix 28
- A list of potential firms eligible for this project is presented in the Appendix 29
- Stakeholder Objectives from the Procurement 32
- Activity Category Estimated cost Procurement Arrangement 36
- Independent environmental monitoring 36
- Consulting service 36
- USD 300000 per contract 36
- CQS 36
- Project monitoring and evaluation 36
- Consulting service 36
- USD 300000 per contract 36
- CQS 36
- Financial audit Consulting service 36
- USD 300000 per contract 36
- CQS 36
- World Bank Procurement Regulations for IPF Borrowers July 2016 Procurement Regulations 52
- A. The Banks Standard Procurement Documents SPDs 52
- B. National Procurement Arrangements 52
- National Procurement Laws 52
- C. Leased Assets 53
- D. Procurement of Second Hand Goods 53
- E. Domestic Preference Goods and Works 53
- F. Hands-on Expanded Implementation Support HEIS 53
- G. Other Relevant Procurement Information 53